Ontario Adds 80 MW of Grid Battery Storage in Vaughan and Guelph
Illustrative photo: Z22, Wikimedia Commons, CC BY-SA 4.0, cropped.
Three new battery energy storage facilities are now running in Vaughan and Guelph. The Ontario government announced their completion on November 6, 2026. Together they add 80 megawatts (MW) of capacity and 320 megawatt-hours (MWh) of storage to the provincial grid. That's enough, the province says, to power roughly 80,000 homes during periods of peak demand (Government of Ontario; Alectra Energy Solutions and Convergent Energy and Power).
Energy and Mines Minister Stephen Lecce attended a tour and ribbon-cutting at the largest of the three sites, Vaughan 3 on Rutherford Road. Two of the three sites are in Vaughan, part of the GTA, and the third is in Guelph. Here's what was built, who built it, and how it fits into Ontario's wider push for battery storage.
The Three Projects
The facilities were delivered by Ontario-based Alectra Energy Solutions in partnership with Convergent Energy and Power, which describes itself as a provider of energy storage solutions in North America. Alectra Energy Solutions' parent company, Alectra Inc., is the electric utility for homes and businesses across much of Southern Ontario. The Alectra companies say they serve more than one million homes and businesses in 17 communities in the Greater Golden Horseshoe.
| Facility | City | Address | Power / energy | Grid connection |
|---|---|---|---|---|
| Vaughan 3 Energy Storage 1 LP | Vaughan | 6531 Rutherford Rd. | 40 MW / 160 MWh | 27.6 kV |
| Vaughan 1E Energy Storage 1 LP | Vaughan | 8118 Dufferin St. | 20 MW / 80 MWh | 27.6 kV |
| Arlen Energy Storage 1 LP | Guelph | 436 Clair Rd. W. | 20 MW / 80 MWh | 13.8 kV |
| Total | 80 MW / 320 MWh |
Source: Alectra Energy Solutions and Convergent Energy and Power, November 6, 2026.
Each site's energy rating is four times its power rating. In other words, each one can run at full output for about four hours before it needs to recharge. The province describes all three as lithium-ion facilities "built on existing municipal energy infrastructure" (Government of Ontario).

Vaughan 3 (Vaughan): 40 MW / 160 MWh. Vaughan 1E (Vaughan): 20 MW / 80 MWh. Arlen (Guelph): 20 MW / 80 MWh. Total 80 MW / 320 MWh. Sources: Government of Ontario and Alectra/Convergent releases, Nov 6, 2026.
How They Were Procured
All three projects won contracts in the Independent Electricity System Operator's (IESO) Expedited Long-Term 1 (E-LT1) procurement. The developers say they were awarded in 2023 and now run under 20-year contracts with the IESO (Alectra and Convergent).
The IESO's final E-LT1 results, dated September 18, 2023, list the three projects under the proponent Alectra Convergent Development LP. The contracted capacity is slightly below the nameplate figures: 38 MW for Vaughan 3 and 19 MW each for Vaughan 1E and Arlen (IESO E-LT1 Selected Proponents).
Across all storage projects, E-LT1 selected about 930 MW of nameplate capacity, or 881.7 MW of contracted capacity, from 15 projects. The province rounds this to "roughly 880 MW" and says this first wave expanded Ontario's active battery storage fleet to five times its previous size (Government of Ontario).
What Grid Batteries Do
Battery storage charges when electricity demand is low and sends power back to the grid when demand peaks. According to Alectra and Convergent, this gives the IESO "greater flexibility to balance electricity supply and demand." In remarks quoted by the developers, Minister Lecce said the storage expansion "sends low-cost off-peak nuclear power back to the grid during peak demand."
A battery doesn't generate electricity of its own. Its value is in timing: it shifts energy from hours when demand is low to the hours when the system needs it most.
The Bigger Picture
The government framed the announcement as part of a fast build-out of storage across the province:
- From 228 MW to nearly 3,000 MW. Three years ago, Ontario had just 228 MW of energy storage, most of it at a single pumped storage facility. The province says it has now secured nearly 3,000 MW of battery storage through a series of competitive procurements.
- Demand growth. The IESO forecasts that Ontario's electricity demand could increase by up to 90 per cent by 2050, driven by population growth, manufacturing investment and electrification, according to the release.
- Growing host communities. The province says Vaughan expects nearly 576,000 residents and more than 354,000 jobs by 2051, and that Guelph expects its population to grow by 40 per cent over the next 30 years.
- New supply overall. IESO President and CEO Jason Fitzsimmons said the projects are part of "the over 9,000 MW of new and re-contracted domestic supply that has been secured over the past five years."
The figures in this section come from the Government of Ontario's November 6 release. The release does not explain how it calculated the "80,000 homes" figure.
What the Industry Said
Several sector groups welcomed the projects in the government's release:
- Electricity Distributors Association: President and CEO Teresa Sarkesian said storage "can play a valuable role alongside broader investments in distribution infrastructure, helping to modernize the grid."
- Ontario Energy Association: President and CEO Vince Brescia said that by using existing infrastructure, "these resources reduce the need for more costly new infrastructure and benefit Ontario ratepayers."
- Energy Storage Canada: President and CEO Justin Rangooni said the projects add "flexible capacity to the grid."
- Canadian Renewable Energy Association: President and CEO Vittoria Bellissimo said CanREA "looks forward to building on this momentum through future procurements."
What to Watch
E-LT1 was the first, expedited round of long-term contracts. In June 2026, the IESO announced the results of the first capacity window of its Second Long-Term RFP (LT2): 20-year contracts for three new-build battery storage facilities totalling 640 MW. The IESO says this brings Ontario's total battery storage to "over 3,500 MW by 2030." It also says the LT2 batteries were procured at a price 36 per cent lower than E-LT1 battery storage (IESO).
More LT2 windows are planned. In an August 2026 engagement presentation, the IESO's approximate timeline showed final Window 2 documents in the first quarter of 2027 and contract awards in the first quarter of 2028. The IESO notes that these dates could change (IESO LT2 Window 2 presentation).
For more on how Ontario's construction and electrical sector is performing, see our Q3 2026 Toronto construction and electrical insights report.
Electro Group is a licensed Toronto electrical contractor serving residential, commercial and institutional clients.
Sources
All accessed November 16, 2026.
- Government of Ontario, Ontario Completes Three New Energy Storage Projects on Time and on Budget, news release, November 6, 2026.
- Alectra Energy Solutions and Convergent Energy and Power, Alectra Energy Solutions and Convergent Energy and Power Complete Three Battery Storage Facilities Supporting Ontario's Electricity Grid, news release, November 6, 2026.
- Independent Electricity System Operator, Expedited Long-Term RFP (E-LT1 RFP) Selected Proponents: Final Results, September 18, 2023.
- Independent Electricity System Operator, Long-Term 2 Capacity Stream Results Announced, June 19, 2026.
- Independent Electricity System Operator, Long Term 2 (LT2) RFP: Window 2, engagement presentation, August 20, 2026.